Discrete-event simulation of truck–excavator systems in surface mining using a finite-source closed-loop queuing model

Authors

DOI:

https://doi.org/10.30656/jsmi.v9i2.11003

Keywords:

Closed-loop queuing model, DES, Match factor, Mining simulation, Queuing theory, Truck–excavator system

Abstract

Truck-excavator interaction in surface mining is often modeled as finite-source, closed-loop queuing systems. An optimization-based approach is typically used, assuming deterministic and homogeneous fleet configurations. This paper aims to contribute to the current literature by implementing a simulation-based approach, discrete-event simulation (DES), to analyze a finite-source closed-loop queuing model in a surface mining operation. The case study used was coal overburden removal activities, which operate under a first-come, first-served discipline, and loop through four phases: loading, hauling, dumping, and returning. Under the current fleet configuration, the overburden removal activity is experiencing a 19,17% production shortfall and a match factor (MF) of 0.74. An MF below 1 indicates an under-truck system, where the excavator often idles while waiting for the trucks to arrive.  Three scenarios were tested using the validated DES model: (1) the as-is scenario with four trucks and one excavator, (2) variations of truck quantity, and (3) a route improvement scenario to reduce travel time. Simulation results indicate that adding five trucks yields the highest productivity (533.86 BCM/hour), utilization (92.48%), and MF (0.91), while the route improvement scenario achieved nearly comparable performance (513.94 BCM/hour, 88.86% utilization, MF = 0.88) with lower resource. Although the current case study operates under a homogeneous fleet with a single excavator, this study also tests the DES model under heterogeneous fleet configurations and a multi-server setup involving two excavators. These findings highlight the DES capability in modeling and analyzing a queuing system under a finite-source closed-loop, both for homogeneous and heterogeneous fleet configurations.

Downloads

Download data is not yet available.

References

[1] M. Abolghasemian, A. G. Kanafi, and M. Daneshmand-Mehr, “Simulation‐Based Multiobjective Optimization of Open‐Pit Mine Haulage System: A Modified‐NBI Method and Meta Modeling Approach,” Complexity, vol. 2022, no. 1, pp. 1–15, Jan. 2022, doi: https://doi.org/10.1155/2022/3540736.

[2] M. Abolghasemian, M. Daneshmand-Mehr, and A. Ghane, “A Two-Phase Simulation-Based Optimization of Hauling System in Open-Pit Mine,” Iran. J. Manag. Stud., vol. 13, no. 4, pp. 705–732, 2020, doi: https://doi.org/10.22059/ijms.2020.294809.673898.

[3] K. Elijah, G. Joseph, M. Samuel, and D. Mauti, “Optimisation of shovel-truck haulage system in an open pit using queuing approach,” Arab. J. Geosci., vol. 14, no. 11, p. 973, Jun. 2021, doi: https://doi.org/10.1007/s12517-021-07365-z.

[4] J. Matsimbe, “Optimization of Shovel-Truck Productivity in Quarries,” Int. J. Res. Advent Technol., vol. 8, no. 10, pp. 1–9, Nov. 2020, doi: https://doi.org/10.32622/ijrat.810202008.

[5] B. Ozdemir and M. Kumral, “Simulation-based optimization of truck-shovel material handling systems in multi-pit surface mines,” Simul. Model. Pract. Theory, vol. 95, pp. 36–48, Sep. 2019, doi: https://doi.org/10.1016/j.simpat.2019.04.006.

[6] S. V. Manyele, “Investigation of Excavator Performance Factors in an Open-Pit Mine Using Loading Cycle Time,” Engineering, vol. 09, no. 07, pp. 599–624, 2017, doi: https://doi.org/10.4236/eng.2017.97038.

[7] D. Sembakutti, M. Kumral, and A. P. Sasmito, “Analysing equipment allocation through queuing theory and Monte-Carlo simulations in surface mining operations,” Int. J. Min. Miner. Eng., vol. 8, no. 1, p. 56, 2017, doi: https://doi.org/10.1504/IJMME.2017.082693.

[8] E. Y. Baafi and W. Zeng, “A Discrete-Event Simulation for a Truck-Shovel System,” in Proceedings of the 27th International Symposium on Mine Planning and Equipment Selection - MPES 2018, Cham: Springer International Publishing, 2019, pp. 265–276. doi: https://doi.org/10.1007/978-3-319-99220-4_22.

[9] G. Kappas and T. M. Yegulalp, “An application of closed queueing networks theory in truck-shovel systems,” Int. J. Surf. Mining, Reclam. Environ., vol. 5, no. 1, pp. 45–51, Jan. 1991, doi: https://doi.org/10.1080/09208119108944286.

[10] W. Morgan and L. Peterson, “Determining Shovel Truck Productivity,” Min. Eng., vol. 20, no. 12, pp. 76–80, 1968, [Online]. Available: https://www.scribd.com/document/319097344/Determining-Shovel-Truck-Productivity

[11] M. R. Taufiq, F. A. R. Putri, and Y. Fanani, “Productivity Analysis of Digging, Loading, and Hauling Equipment in Overburden Removal Activities at PT. Anugrah Borneo Sinergy in Keramat Mina field, South Kalimantan, Indonesia,” J. Earth Mar. Technol., vol. 5, no. 1, pp. 66–79, Dec. 2024, doi: https://doi.org/10.31284/j.jemt.2024.v5i1.6426.

[12] M. F. Isnafitri, C. N. Rosyidi, and A. Aisyati, “A Truck Allocation Optimization Model in Open Pit Mining to Minimize Investment and Transportation Costs,” IOP Conf. Ser. Mater. Sci. Eng., vol. 1096, no. 1, p. 012024, Mar. 2021, doi: https://doi.org/10.1088/1757-899X/1096/1/012024.

[13] R. Fikri and M. Gusman, “Analysis Match Factor Loader and Hauler for Activities Overburden Removal Using the Queue Method at PT Andalan Artha Primanusa Jobsite PT Budi Gema Gempita, South Sumatera Province,” Min. Dev. J., vol. 9, no. 1, pp. 1–10, 2024, [Online]. Available: https://ejournal.unp.ac.id/index.php/mining/article/view/127642

[14] L. J. S. Palayukan, A. V Anas, and P. Purwanto, “The Effect of Overburden Loader and Hauler Match Factor on Fuel Consumption and Cost Using Queueing Theory (Case Study: Coal Mining PT. Perkasa Inakakerta East Kalimantan Province),” Int. J. Eng. Appl. Sci., vol. 6, no. 2, pp. 72–84, 2019, doi: https://doi.org/10.20956/ijesca.v6i2.2073.

[15] A. Permana, S. Ubud, and D. S. Kanto, “Optimization of Heavy Equipment Capabilities in The Framework of Productivity and Coal Mining Business Sustainability: Case Study of East Kalimantan Mining Area,” J. Econ. Bus., vol. 3, no. 4, pp. 1673–1688, Dec. 2020, doi: https://doi.org/10.31014/aior.1992.03.04.312.

[16] N. Rokbani et al., “Bi-heuristic ant colony optimization-based approaches for traveling salesman problem,” Soft Comput., vol. 25, no. 5, pp. 3775–3794, Mar. 2021, doi: https://doi.org/10.1007/s00500-020-05406-5.

[17] T. Z. Khalaf, H. Çağlar, A. Çağlar, and A. N. Hanoon, “Particle Swarm Optimization Based Approach for Estimation of Costs and Duration of Construction Projects,” Civ. Eng. J., vol. 6, no. 2, pp. 384–401, Feb. 2020, doi: https://doi.org/10.28991/cej-2020-03091478.

[18] H. H. Ghaziania, M. Monjezi, A. Mousavi, H. Dehghani, and E. Bakhtavar, “Design of loading and transportation fleet in open-pit mines using simulation approach and metaheuristic algorithms,” J. Min. Environ., vol. 12, no. 4, pp. 1177–1188, 2021, doi: https://doi.org/10.22044/jme.2022.11450.2131.

[19] H. H. Turan, M. Atmis, F. Kosanoglu, S. Elsawah, and M. J. Ryan, “A risk-averse simulation-based approach for a joint optimization of workforce capacity, spare part stocks and scheduling priorities in maintenance planning,” Reliab. Eng. Syst. Saf., vol. 204, p. 107199, Dec. 2020, doi: https://doi.org/10.1016/j.ress.2020.107199.

[20] E. Asa, “Using simulation to optimize excavator truck selection,” Cost Eng., vol. 49, no. 10, pp. 12–17, 2017, [Online]. Available: https://www.proquest.com/docview/220460011

[21] E. Torkamani and H. A. Nasab, “A linkage of truck-and-shovel operations to short-term mine plans using discrete-event simulation,” Int. J. Min. Miner. Eng., vol. 6, no. 2, p. 97, Jan. 2015, doi: https://doi.org/10.1504/IJMME.2015.070367.

[22] M. A. May, “Applications of queuing theory for open-pit truck/shovel haulage systems,” Virginia Tech, 2013. [Online]. Available: https://vtechworks.lib.vt.edu/items/fecf61c3-860b-4671-91ed-09549ddad265

[23] D. Zinoviev, “Discrete Event Simulation: It’s Easy with SimPy!,” Comput. Sci., 2024, doi: https://doi.org/10.48550/arXiv.2405.01562.

[24] C. N. Burt and L. Caccetta, “Match factor for heterogeneous truck and loader fleets,” Int. J. Mining, Reclam. Environ., vol. 22, no. 1, pp. 84–85, Mar. 2008, doi: https://doi.org/10.1080/17480930801943334.

[25] R. Friswell and A. Williamson, “Management of heavy truck driver queuing and waiting for loading and unloading at road transport customers’ depots,” Saf. Sci., vol. 120, pp. 194–205, Dec. 2019, doi: https://doi.org/10.1016/j.ssci.2019.06.039.

[26] M. I. Kulula and J. M. Akande, “Effects of Machine Parameter and Natural Factors on the Productivity of Loading and Haulage Equipment,” J. Miner. Mater. Charact. Eng., vol. 06, no. 01, pp. 139–153, 2018, doi: https://doi.org/10.4236/jmmce.2018.61011.

[27] Y. T. Prasetyo, M. Paradise, and F. Mukarrom, “Productivity Assessment of Digging and Loading Equipment (Cat 330D2L) and Hauling Equipment (Fuso 220PS) in Coal Mining at PT. Bhumi Sriwijaya Perdana Coal, Musi Banyuasin Regency, South Sumatra,” Indones. J. Earth Sci., vol. 4, no. 2, p. A1226, Dec. 2024, doi: https://doi.org/10.52562/injoes.2024.1226.

[28] O. Litvin and Y. Litvin, “Evaluation of Effect of the Excavator Cycle Duration on its Productivity,” E3S Web Conf., vol. 174, p. 01010, Jun. 2020, doi: https://doi.org/10.1051/e3sconf/202017401010.

[29] A. D. Suhendar, A. Nurmansyah, P. Pramuditha, and E. Santo, “Operations Management in Measuring the Operational Effectiveness and Efficiency in Company Engaged in Mining Industri,” JURISMA J. Ris. Bisnis Manaj., vol. 14, no. 2, pp. 329–340, Nov. 2024, doi: https://doi.org/10.34010/jurisma.v14i2.12855.

[30] M. Šopić, M. Vukomanović, D. Car-Pušić, and I. Završki, “Estimation of the excavator actual productivity at the construction site using video analysis,” Organ. Technol. Manag. Constr. an Int. J., vol. 13, no. 1, pp. 2341–2352, Jan. 2021, doi: https://doi.org/10.2478/otmcj-2021-0003.

[31] M. Al-Masri, “An approach for Evaluating the Full Truck and Full Bucket Loading Strategies in Open-Pit Mining Using a Discrete Event Simulation and Machine Learning,” 2022. [Online]. Available: https://ualberta.scholaris.ca/items/03c8a4e1-cb0b-4311-9ae2-23934bf2ed96

[32] E. Zankoul, H. Khoury, and R. Awwad, “Evalutation of Agent-Based and Discrete-Event Simulation for Modeling Construction Earthmoving Operations,” in 32nd International Symposium on Automation and Robotics in Construction and Mining, Jun. 2015. doi: https://doi.org/10.22260/ISARC2015/0014.

[33] T. Khajvandsany, H. Amoozadkhalili, R. Rezaeyan, and K. Nemati, “Optimization of multi-objective simulation of excavator-truck loading system for mining minerals,” Eng. Manag. Soft Comput., vol. 10, no. 2, pp. 182–203, 2025, doi: https://doi.org/10.22091/jemsc.2025.11807.1229.

[34] M. Fisonga and V. Mutambo, “Optimization of the fleet per shovel productivity in surface mining: Case study of Chilanga Cement, Lusaka Zambia,” Cogent Eng., vol. 4, no. 1, p. 1386852, Jan. 2017, doi: https://doi.org/10.1080/23311916.2017.1386852.

Downloads

Published

2025-12-29

Issue

Section

Research Article

How to Cite

[1]
D. Setiawan, H. Haswika, Q. Qurtubi, and M. Z. Z. . Alfieta, “Discrete-event simulation of truck–excavator systems in surface mining using a finite-source closed-loop queuing model”, j. sist. manaj. ind., vol. 9, no. 2, pp. 125–134, Dec. 2025, doi: 10.30656/jsmi.v9i2.11003.