Evaluasi Penjadwalan Waktu dan Biaya pada Pembuatan Crude Storage Tank (600 Mb) Menggunakan Metode Critical Path Method

  • Muhamad Ridwan Universitas Serang Raya
  • Supriyadi Supriyadi Universitas Serang Raya
  • Tri Joko Wibowo Universitas Serang Raya
Abstract views: 2277 , PDF downloads: 82
Keywords: Critical Path Method, Gantt Chart, Scheduling, Critical Path, Project Acceleration

Abstract

The company uses the Gantt Chart method for scheduling planning, but this method has several disadvantages, that is, it cannot explicitly indicate the relationship between activities and how one activity results in other activities if the time is late or accelerated. To determine the optimal duration and the total cost of building 1 (one) Crude Storage Tank capacity of 600 MB (Mega Barrel) an optimization of the duration of the project is needed so that it can be known how long a project is completed and looking for possible acceleration of project time using the Critical method Path Method is a method used to make project scheduling. By using the Critical Path Method method the work of building 1 (one) Crude Storage Tank with a capacity of 600 MB (Mega Barrel) on the Open Access (Phase-1) RU-II Dumai project, can be completed within a period of 384 days/64 weeks, and trajectory critical lies in the b-c-d-e-f-j-l activity with a total cost of Rp.15,086,074,328.

Downloads

Download data is not yet available.

References

Astutik, F. (2015). Pengoptimalisasi Pelaksanaan Proyek Pembangunan Gedung Pasca Sarjana IAIN Tulungagung Dengan Menggunakan Metode CPM. Fakultas ekonomi. Universitas Nusantara PGRI Kediri.

Badri, S. (2001). Dasar-dasar Network planning. Jakarta. Rineka Cipta.

Habibi, A., Supriyadi, S., & Wibowo, T. J. (2016). Analisis Penjadwalan Pembuatan Heat Exchanger Menggunakan Critical Path Method. Jurnal INTECH Teknik Industri Universitas Serang Raya, 2(1), 19–27.

Proboyo, B. (1999). Keterlambatan Waktu Pelaksanaan Proyek Klasifikasi dan Peringkat dari Penyebab-penyebabnya. Civil Engineering Dimension, 1(1), 46–58.

Shankar, N. R., Sireesha, V., & Rao, P. P. B. (2010). An analytical method for finding critical path in a fuzzy project network. International Journal of Contemporary Mathematical Sciences, 5(20), 953–962.

Soeharto, I. (1997). Manajemen proyek dari konseptual sampai operasional. Jakarta: Erlangga.

Taurusyanti, D., & Lesmana, M. F. (2015). Optimalisasi Penjadwalan Proyek Jembatan Girder Guna Mencapai Efektifitas Penyelesaian Dengan Metode PERT dan CPM Pada PT Buana Masa Metalindo. JIMFE (Jurnal Ilmiah Manajemen Fakultas Ekonomi), 1(1), 32–36.

Yamin, R. A., & Harmelink, D. J. (2001). Comparison of linear scheduling model (LSM) and critical path method (CPM). Journal of Construction Engineering and Management, 127(5), 374–381.

PlumX Metrics

Published
2016-12-28
How to Cite
Ridwan, M., Supriyadi, S., & Wibowo, T. J. (2016). Evaluasi Penjadwalan Waktu dan Biaya pada Pembuatan Crude Storage Tank (600 Mb) Menggunakan Metode Critical Path Method. Jurnal INTECH Teknik Industri Universitas Serang Raya, 2(2), 91-98. https://doi.org/10.30656/intech.v2i2.870
Section
Articles