Evaluasi Penjadwalan Waktu dan Biaya pada Pembuatan Crude Storage Tank (600 Mb) Menggunakan Metode Critical Path Method

  • Muhamad Ridwan Universitas Serang Raya
  • Supriyadi Supriyadi Universitas Serang Raya
  • Tri Joko Wibowo Universitas Serang Raya
Abstract views: 2198 ,

Abstract

The company uses the Gantt Chart method for scheduling planning, but this method has several disadvantages, that is, it cannot explicitly indicate the relationship between activities and how one activity results in other activities if the time is late or accelerated. To determine the optimal duration and the total cost of building 1 (one) Crude Storage Tank capacity of 600 MB (Mega Barrel) an optimization of the duration of the project is needed so that it can be known how long a project is completed and looking for possible acceleration of project time using the Critical method Path Method is a method used to make project scheduling. By using the Critical Path Method method the work of building 1 (one) Crude Storage Tank with a capacity of 600 MB (Mega Barrel) on the Open Access (Phase-1) RU-II Dumai project, can be completed within a period of 384 days / 64 weeks, and trajectory critical lies in the b-c-d-e-f-j-l activity with a total cost of Rp.15,086,074,328.

Downloads

Download data is not yet available.

PlumX Metrics

Published
2016-12-28
How to Cite
Ridwan, M., Supriyadi, S., & Wibowo, T. J. (2016). Evaluasi Penjadwalan Waktu dan Biaya pada Pembuatan Crude Storage Tank (600 Mb) Menggunakan Metode Critical Path Method. Jurnal INTECH Teknik Industri Universitas Serang Raya, 2(2). https://doi.org/10.30656/intech.v2i2.870
Section
Articles