Usulan Perbaikan Proses Cross Drainage untuk Mempercepat Waktu Proyek Pembangunan Jalan Raya

  • Mohamad Jihan Shofa Universitas Serang Raya
  • Lanis Listiyana Universitas Serang Raya
  • Dadi Cahyadi Universitas Serang Raya
Abstract views: 402 , PDF downloads: 796
Keywords: Borda, Cross Drainage, Critical Path Method, Fishbone Diagram

Abstract

The success of the project can be judged by the timeliness of the planned target. The problem in the highway project is in the difference between cross drainage age implementation and the age of the project plan that has been set, so that, the project becomes not timely. This research aims to evaluate the critical path of cross drainage project, and what improvements are appropriate in the framework of project acceleration. The Critical Path Method (CPM) method is used to determine the critical path of the cross drainage project activity, from which critical path will be analyzed by using the Fishbone Diagram. Furthermore, borda technique is used to determine the appropriate improvement.

Downloads

Download data is not yet available.

References

Antill, J. M., & Woodhead, R. W. (1990). Critical path methods in construction practice. John Wiley & Sons.

Asmaroni, D. (2016). Analisa Keterlambatan Waktu Pelaksanaan Proyek Pembangunan Gedung Pemerintah di Kabupaten Pamekasan. REKAYASA: JURNAL SIPIL, 1(1), 19–23.

Cahyana, N. H. (2014). Group Decision Support System (GDSS) Untuk Menentukan Prioritas Proyek. Telematika, 10(2), 147–152.

Heizer, J., & Render, B. (2005). Operation Management (Manajemen Operasi) Edisi Ketujuh. Jakarta: Salemba Empat.

Idrus, T. Al. (2018). Faktor-Faktor yang Mempengaruhi Keputusan Nasabah dalam Memilih Produk Rahn di Pegadaian Syariah Ar Hakim Medan dengan Cabang Metode Borda.Skripsi. Universitas Sumatera Utara.

Mudzakir, A. C., Setiawan, A., Wibowo, M. A., & Khasani, R. R. (2017). Evaluasi Waste Dan Implementasi Lean Construction (Studi Kasus: Proyek Pembangunan Gedung Serbaguna Taruna Politeknik Ilmu Pelayaran Semarang). JURNAL KARYA TEKNIK SIPIL, 6(2), 145–158.

Nalhadi, A., & Suntana, N. (2017). Analisa Infrastruktur Desa Sukaci-Baros Dengan Metode Critical Path Method (CPM). Jurnal Sistem Dan Manajemen Industri, 1(1), 35–42.

Setiawati, S. (2017). Penerapan Metode CPM Dan PERT Pada Penjadwalan Proyek Konstruksi (Studi Kasus: Rehabilitasi/Perbaikan Dan Peningkatan Infrastruktur Irigasi Daerah Lintas Kabupaten/Kota DI Pekan Dolok). Skripsi. Universitas Sumatera Utara.

Taurusyanti, D., & Lesmana, M. F. (2015). Optimalisasi Penjadwalan Proyek Jembatan Girder Guna Mencapai Efektifitas Penyelesaian Dengan Metode PERT dan CPM Pada PT Buana Masa Metalindo. JIMFE| Jurnal Ilmiah Manajemen Fakultas Ekonomi, 1(1), 32–36.

Zareei, S. (2018). Project scheduling for constructing biogas plant using critical path method. Renewable and Sustainable Energy Reviews, 81, 756–759.

PlumX Metrics

Published
2018-12-30
How to Cite
Shofa, M. J., Listiyana, L., & Cahyadi, D. (2018). Usulan Perbaikan Proses Cross Drainage untuk Mempercepat Waktu Proyek Pembangunan Jalan Raya. Jurnal INTECH Teknik Industri Universitas Serang Raya, 4(2), 71-76. https://doi.org/10.30656/intech.v4i2.1054
Section
Articles