Analisa Perencanaan Kebutuhan Material pada Perusahaan Manufaktur Kertas dengan Metode Material Requirement Planning (MRP)

Authors

  • Sri Lestari Universitas Muhammadiyah Tangerang
  • Distian Dwi Nurdiansah Universitas Muhammadiyah Tangerang

DOI:

https://doi.org/10.30656/intech.v4i2.956

Keywords:

Fixed Period Requirements, Forecasting, Lot For Lot, Material Requirement Planning

Abstract

The development of the business world is currently experiencing a very rapid growth rate. Planning for the proper procurement of materials will be able to facilitate the company's production activities. Production process activities in companies often experience problems such as inaccurate production, which is caused by delays in the arrival of raw materials, and damage to raw materials due to too long storing in warehouses. This study aims to plan future needs with the Material Requirement Planning (MRP) approach by doing forecasting, making the Master Production Schedule (MPS), Material Requirement Planning (MRP) and conducting a cost analysis of the five methods used. The results of this study are forecasting product demand will be used linear regression method, and effective material requirements planning method with the lowest cost is to use the Lot For Lot (LFL) method of $ 164.48. The application of the Lot For Lot method can reduce costs by 90.06% compared to the Fixed Period Requirements (FPR) method used by the company.

Downloads

Download data is not yet available.

References

Arif, M., Supriyadi, S., & Cahyadi, D. (2017). Analisis Perencanaan Persediaan Batubara FX Dengan Metode Material Requirement Planning. Jurnal Manajemen Industri dan Logistik, 1(2), 53-60.

Chase R B., Jacobs R F., & Aquilano N J. (2004). Operations Management For Competitive Advantage. New York: Mc Graw Hill.

Dewi, P. S., & Saroso, D. S. (2016). Implementasi Material Requirements Planning (MRP) pada Perencanaan Persediaan Material Panel Listrik di PT. TIS. Sinergi: Jurnal Teknik Mercu Buana, 20(1), 36-46.

Ferdinand, E. (2012). Analisis Peramalan Volume Penjualan Dengan Perbandingan Cara Manual Dan Program QSB Pada PT. Lion Wings.

Greasley, A. (2008). Operations management. Operations Management. Thousand Oaks: SAGE Publications Inc.

Heizer, J., & Render, B. (2010). Manajemen Operasi. Jakarta: Salemba Empat.

Herjanto, E. (2008). Manajemen Operasi. Jakarta: PT. Grasindo.

Karuniawan, A., Supriyadi, S., & Ramayanti, G. (2017). Optimalisasi Sistem Persediaan Bahan Baku Natrium Persulfate Dengan Metode Lot Sizing. In Prosiding Seminar Nasional Riset Terapan| SENASSET (pp. 151-157).

Milne, R. J., Mahapatra, S., & Wang, C. T. (2015). Optimizing planned lead times for enhancing performance of MRP systems. International Journal of Production Economics, 167(1), 220–231.

Savira, M., & Moeliono, N. N. K. (2014). Analisis Peramalan Penjualan Obat Generik Berlogo (Ogb) Pada Pt. Indonesia Farma. eProceedings of Management,1(3), 1-13

Sungkawa, I., & Megasari, R. T. (2011). Penerapan Ukuran Ketepatan Nilai Ramalan Data Deret Waktu dalam Seleksi Model Peramalan Volume Penjualan PT Satriamandiri Citramulia. ComTech: Computer, Mathematics and Engineering Applications, 2(2), 636-645

Vially, J., & Angreni, I. A. A. (2013). Aplikasi Metode MRP (Material Requirement Planning) Terhadap Material Pasir, Semen Dan Besi Tulangan Pada Konstruksi Jalan Layang. Prosiding PESAT, (pp. T41-T48).

Wahyuni, A., & Syaichu, A. (2015). Perencanaan Persediaan Bahan Baku dengan Menggunakan Metode Material Requirement Planning (MRP) Produk Kacang Shanghai pada Perusahaan Gangsar Ngunut-Tulungagung. Spektrum Industri, 13(2), 141-156.

Downloads

Published

2018-12-27

How to Cite

Lestari, S., & Nurdiansah, D. D. (2018). Analisa Perencanaan Kebutuhan Material pada Perusahaan Manufaktur Kertas dengan Metode Material Requirement Planning (MRP). Jurnal INTECH Teknik Industri Universitas Serang Raya, 4(2), 59–64. https://doi.org/10.30656/intech.v4i2.956